Arundell Barranca Improvments
Over 3,550 lf of an exiting drainage channel was removed and replaced with a new 25 lf wide by 14 lf high concrete rectangular channel. Over 7,000 cubic yards of concrete, 850,000 lbs of steel and 100,000 cubic yards of excavation and removal were required to complete this project. Building the new channel required maintaining the flow in the existing channel while the new one was being constructed. Unexpected heavy rains in May caused extensive damage and required us to accelerate to complete the project before the winter rains hit.
Project Details
Work With Us- Location: Ventura, CA
- Owner: Ventura County Watershed Protection District
- General Contractor: Blois Contruction, Inc.
- Contract Size: $6,498,086