Sewer Brine Line Phase 1-B
Part of a project to increase group water supplies by over 40,000 acre-feet a year for the Calleguas Municipal Water District. Over 8,500 lf of 48″ pipeline was installed in this segment to carry excess brine from the treatment process to the ocean. Due to the corrosive properties of the brine, never before used materials were incorporated into this project, including 48″ C900 PVC fittings and required close coordination with the Owner and the Engineer. Other challenges included a 54″ mirco-tunnel under an existing channel and extensive traffic control on a busy major road.
Project Details
Work With Us- Location: Oxnard, CA
- Owner: Calleguas Municipal Water District
- General Contractor: Blois Contruction, Inc.
- Contract Size: $14,476,899