Western Ave Pump Station
A bond completion project with a tri-party agreement between the District, the surety and Blois Construction. Extensive project management, coordination and communication was required to complete this project that had been partially completed by a prior contractor. Concrete demolition and repair, mechanical piping, HVAC, exhaust piping, misc. steel, fire sprinklers, generator and electrical were all a part of this project. Grading and paving was also required to complete civil improvements on adjacent city streets.
Project Details
Work With Us- Location: San Pedro, CA
- Owner: County Sanitation District No.2 of Los Angeles County
- General Contractor: Blois Contruction, Inc.
- Contract Size: $1,270,478